Why your migration timeline is probably wrong
Migration timelines are systematically optimistic. Here's why and what to do about it.
The pattern
Most migration plans assume the team hits target velocity in week 1 and sustains it. In practice:
- Weeks 1-6: learning the tooling (25-50% of projected velocity)
- Weeks 6-16: hitting stride (projected velocity)
- Weeks 16-24: dependency surprises emerge (50-75% of velocity)
- Weeks 24+: wave fatigue (50-75% of velocity)
Add it all up: you'll finish in 150-180% of planned time.
Why dependency surprises happen
The first waves are the "clean" apps — documented, owned, simple. The assumption is that later waves will be similar. They're not. The back half is where you find:
- The undocumented app that three critical apps depend on
- The team that owned the app just quit
- The database with a schema nobody fully understands
- The vendor integration using hard-coded IP addresses
What to do differently
1. Pad the middle and end
Allocate 30-40% of timeline to the last 25% of apps. Not because they're harder individually, but because the discovery overhead catches up.
2. Front-load dependency mapping
Before you start, run the Server Inventory & Dependency Mapper across EVERY app, not just wave 1. Most surprises are discoverable if you look.
3. Budget a "wave 0" for tooling
Spend the first month getting the migration factory running: IaC templates, CI/CD, monitoring, runbooks. Every subsequent wave uses this factory.
4. Define "done" precisely
"Migrated" means running in cloud AND decommissioned on-prem AND validated for 30 days AND owner sign-off. Teams that skip the last three items are secretly running parallel environments for 6+ months extra.